The answer in this case is, lead cheeks! - on the middle bedroom dormer sides. That just about completes the roof.
Inside, sanitary ware is being fitted as are the utility room cupboards. The Template Man measured up the main island and the toaster nook yesterday and they've gone away to mill out the holes in the worktop.
There had been a problem with the double glazing units which apparently got damaged in transit and had to be remade - the team have been fitting those today. And as you can see James-the-Digger has been at work laying the base for the driveway.
The pic below shows some of the boys, who are there around 7am in the morning, collapsed with a cuppa at the end of the day.