Saturday, 14 May 2016

One Year Out!! - and practically complete...

This post is a couple of days late - I should have posted on 11 May which was one year since the building works started.  As it happens, that's the day that the architect came round to do a final inspection and pronounced 'practical completion'.  This is official recognition that it's fundamentally finished, although there's still a short list of stuff to deal with, not necessarily now.  We also have the building inspector's completion certificate, and now we have to pay the just-about-final bill.  For those who don't know the process, there's a retention of part of the contract cost to cover any works that arise during the following year, so there's a small bucket of fixing-money for anything else that pops up.  Milestone!