...or not.  The roof has been fully battened and the gulleys leaded for long enough that we're getting frustrated with the lack of slate on the roof.  Pat and Judy - you commented that you are looking forward to seeing it done - well, I can tell you - so are we!!!!
Tantalisingly, the slates are stacked up on the scaffolding
 but not yet on the roof, apart from this line here:


However, both end gables, the garage gable and part of the main rear gable are now zinc clad and looking great.

Meanwhile indoors is coming on nicely - the bathrooms both have walls - this is the main bathroom and that's the MVHR you can see waiting to be installed over the garage. And in answer to John's question - the bifolds look very good, although the scaffolding does somewhat diminish the full effect!